Espanola council approves design plans for bridge

The Black Creek Bridge replacement project is moving forward.

Espanola council has unanimously agreed to have the final detailed design plans completed for $208,000.

This process is expected to take 17 weeks and construction is estimated at 12-16 weeks.

It is anticipated that the full cost of the design and construction can be 100% funded by the Ontario Community Infrastructure Funding allocations as there are approximately three years outstanding for a total of $819,500.

This project will also fall under the 2021 municipal budget.

Background:
 Black Creek bridge was rehabilitated in 2006. It should be noted that only light repairs could be completed on the cribbing and that the steel
beams and Girders remained as well.
 2016 Bridge Inspection report, from EXP, forecasted bridge replacement in 2022-2026.
 Bridges have mandatory inspection requirements and the bridge was reinspected in the fall of 2020. The report concluded that the bridge
was at the end of life needs and needs immediate replacement. The report also noted that any observed deterioration should immediately
close the bridge to all traffic.
 Council approved a hydrology study. The study would help determine design parameters and determine if an Environmental assessment
would be needed.
 It was determined that an Environmental Assessment (EA) would not be needed saving the municipality approximately $145,000 in the cost
of an EA.

Analysis:
 RVA has submitted a proposal for the Engineering Services in the sum of $208,000. This price includes the following.
1. Topographic Survey for the creation of drawings.
2. Geotechnical Investigation for determining soil types and structural capacity.
3. Milestone meeting with the Corporation to evaluate design options.
4. Assist with the Public information to advise and discuss with stakeholders that may be affected by the replacement of the bridge.
5. Consult and seek any necessary approvals from MECP/MNRF/DFO these consultations could impact design.
6. Detailed design specifications and tender.
7. Contract Administration and site supervision.

 This investment doesn’t include actual bridge construction costs. The inspection report suggested a new bridge estimate $4 ,500/m2 or $210,000. However, until the detailed design is complete staff will update the council.

 

https://pub-espanola.escribemeetings.com/filestream.ashx…

https://pub-espanola.escribemeetings.com/filestream.ashx…

https://pub-espanola.escribemeetings.com/filestream.ashx…

Rosalind Russell
Rosalind Russellhttp://myespanolanow.com
Rosalind is Vista Radio's CJJM 99.3 FM - CJJM - Espanola's long-time Morning Announcer and Regional News Anchor/Journalist covering the districts of Sudbury, Algoma and Manitoulin. With a career in multi-media spanning the last 45 years, she has expertise in radio, television, newspaper and magazine writing. A long-time volunteer, she is the Inaugural 2025 Senior of the Year Award representing the Town of Espanola and represented women empowerment as the national 2024 Ms. Elite Regional Canada titleholder. A mother of five, and grandmother of two says simply, "I am the Queen of my Universe, and my children/grandchildren are my Crowning Jewels." Volunteering, pageants, reading and writing are her passions. If you have a story to share, email Roz at: [email protected] or call 1705-869-NEWS (6397).

Continue Reading

cknr Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Marking National Day for Truth & Reconciliation in Espanola

The Town of Espanola is partnering with Noojmowin Teg Health Centre to host a mini–Pow Wow Social on September 30th in recognition of the National Day for Truth & Reconciliation.

Annual General Meeting slated for Espanola Little Theatre

The Espanola Little Theatre will be hosting its Annual General Meeting next week.

Hatchery Pond prepped for new fry

The Hatchery Pond overseen by the North Shore Anglers and Hunters Conservation Association has undergone a major cleanup to prepare it for the raising of new fry in the new year.

Time running out on Dean Lake Road Bridge

The Township of Huron Shores is hosting a public forum this fall focusing on the Dean Lake Road Bridge, but there are concerns the bridge will not be open for winter travel.

Appointment of new Superintendent of Education at the Conseil scolaire du Grand Nord

The Conseil scolaire du Grand Nord has appointed Marie-Soleil Beites as Superintendent of Education.
- Advertisement -